HAU NUI Wind Farm Crane Project
Dear Mr Carter,
following please find our comment to the HAU NUI
Wind Farm Project:
The HAU NUI Wind Farm Project consisted of 7 wind energy converters
to be erected on a 42 m steel tower in a time frame of three weeks.
We were most pleased with the outcome of this project and this was
largely due to the fabulous job and the assistance TITAN Cranes have
given us.
We can say that we possess a far-reaching and broad experience in
hiring crane companies for the erection of WECs. So far we have
erected and installed 1100 units, our monthly turnover with various
crane companies amounts to ca. NZ$ 425,000.--.
We were surprised and pleased how well and experienced TITAN Cranes
were handling this task. The know-how was excellent and we consider
ourselves very fortunate to have had such a competent partner on
site. The cooperation was very flexible and TITAN Cranes were able
to respond to even exceptional demands. The work on site was
executed with great care and due to the permanent presence of TITAN
crew members we felt in safe hands.
ENERCON would reconsider a cooperation with TITAN Cranes at any time
and we look forward to new projects together with them.
Kind regards
ENERCON GmbH |